Project Timeline

2019

  • 100 Year Campus Master Plan developed and presented to the CUE Community. The Master Plan examines the CUE campus in immediate years (2020 to 2030), intermediate years (2030-2075) and long-term years (2075 to 2120)
  • A New Academic Building (NAB) is identified as a priority from the immediate years examination to meet the needs of the increasing student population
  • CUE engages Najfeldt Architects Inc. and Reimagine Architects (previously Manasc Isaac) to develop the first phase of the NAB development, the Student Quadrangle (Quad) and Bridge
  • Najfeldt and Reimagine develop consultation process involving CUE faculty and department staff, civic and community stakeholders

2020

  • Consultations with CUE stakeholders, including department staff and faculty
  • NAB is approved at the November 30 meeting of the CUE Board of Governors, with a proposed capital budget of approximately $40M
  • Construction documents and pre-tender reports are adjusted for consultation feedback, highlighting the need for increased office, research and classroom spaces  

2021

  • Tenders for construction are released and the contract is awarded in June
  • The City of Edmonton approves rezoning of the CUE campus
  • Construction begins on the NAB and Quad in September

2023

  • NAB construction close-out and formal commission scheduled for winter
  • NAB construction scheduled for majority completion by Spring, followed by a move-in and grand-opening ceremony for Fall 2023